Dharahara reconstruction gains momentum

Kathmandu / Mar. 10: The reconstruction of historical Dharahara that was devastated by the 2015 Gorkha earthquake is gaining momentum in a way to complete it by mid-September 2020.

Rajuman Maqnandhar, heritage expert of the National Reconstruction Authority (NRA), shared that almost 33 percent works have been so far completed with the spending of Rs 850 million.

The contract for the reconstruction was awarded to Raman Construction with a deadline to accomplish the task in two years. A budget of Rs 3.48 billion is estimated to be spent for Dharahara reconstruction.

Prime Minister KP Sharma Oli had laid the foundation stone of its reconstruction last year.

Daily 150 workers are being mobilized in the reconstruction of the tower.

The breadth of the new Dharahara is bigger than that of the devastated one. It would also have two lifts and a traditional ladder. The Dharahara is being reconstructed in 42 ropanis of land. RSS

Related News

Comments are closed

TOP NEWSview all

Four-nation championship: Nepal into the final

KMC installs Pelican crossings at 36 key locations

Japan to recruit 20,000 Nepali caregivers for health sector

Mushroom industry opened in Nawalparasi

UML reminds PM to revise provisions of Cooperative Ordinance




Positive Development Media Pvt. Ltd. / Regd. No: 232 / 073-74

Newbaneshwor
Kathmandu, Nepal

4479401


Editor : Mr. Divesh J.B. Rana

Chairperson : Mr. Kishore Thapa


Counter:
Web Counter