PAC gives govt a week to explain Sunkoshi-Marin contract cancellation

Kathmandu / Nov 24: The parliamentary Public Accounts Committee (PAC) has given the government seven days to submit all documents explaining the grounds for cancelling the construction contract of the Sunkoshi-Marin Diversion Multipurpose Project and the decision-making process behind it.
The directive followed discussions with Dinesh Rajouria, Director General of the Department of Water Resources and Irrigation (DoWRI), at the committee meeting on Tuesday. PAC Chairman Bharat Khadka instructed the department to submit the relevant documents within a week, saying further discussions would be held after reviewing them.
The committee’s intervention comes amid questions over the cancellation of an international bidding process for the construction of the project’s dam, powerhouse and associated structures. Six companies had participated in the bidding, three of which qualified in the technical evaluation. However, the department scrapped the procurement process just as preparations were underway to open the financial proposals.
The cancellation has drawn particular scrutiny as the project had already made substantial progress, with its main diversion tunnel having achieved a breakthrough.
During Tuesday’s meeting, Rastriya Swatantra Party lawmaker Manish Jha called for an investigation into who was responsible for cancelling the contract about a year ago, during the transitional government formed after the Gen Z movement, and what prompted the decision.
Another lawmaker, Ganesh Singh Thagunna, questioned why the procurement method and procedures were changed for a project whose construction was already underway and whose tunnel had reached the breakthrough stage.
Responding to the concerns, Rajouria defended the department’s decision, saying the cancellation was legally justified. He explained that the 16th amendment to the Public Procurement Regulations requires the use of the ‘rated point criteria’ evaluation method for procuring complex structures worth more than Rs 1.5 billion, prompting the department to scrap the earlier bidding process.
Launched around six years ago, the Sunkoshi-Marin Diversion Multipurpose Project aims to expand irrigation facilities in drought-prone areas of the eastern and central Terai. Its 13.3-kilometre diversion tunnel achieved a breakthrough two years ago, but construction of the dam, powerhouse and associated structures has yet to proceed.
The project is expected to irrigate around 180,000 bighas of land across five districts—Bara, Rautahat, Sarlahi, Mahottari and Dhanusha—and generate 28 megawatts of hydropower.
The delay in awarding the remaining construction contract has raised concerns over the project’s completion timeline and the timely delivery of its intended irrigation and energy benefits.