Chilime’s power supply restores

hydropower projectRasuwa / Dec 7: Power generation from the Chilime Hydropower Project which had stopped from Wednesday afternoon has now been restored.

The power generation from the 22 MW-capacity hydel project had stopped after the problems in the power transmission line. The power supply has been restored after fixing the problem with the power transmission tower, Nepal Electricity Authority (NEA)’s spokesperson Prabal Adhikari said.

The Chilime Hydropower Centre said that skilled technicians were invited to resume the power supply through maintenance of the national transmission line.

After the disruption in power supply, the entire northern belt in the district including the district headquarters of Dhunche had remained under the darkness. RSS

Related News

Leave a Reply

टाइप गरेर स्पेस थिच्नुहोस् र नेपाली युनिकोडमा पाउनुहोस। (Press Ctrl+g to toggle between English and Nepali OR just Click on the letter). अंग्रेजीमा टाइप गर्न "अ" मा थिच्नुहोस्।

*
Advertise Section 7

TOP NEWSview all

Clean Nepal is possible as over 23 million people are willing to contribute: Khem Sharma

Even though it’s late, victims will get something from the commission: Subedi

Cecil and Harambe; a lesson for Himalayan Republic

Trip Down under

We want real conversion of our students beyond religion: Fr. Boniface Tigga, Regional Superior of Nepal Jesuit Society




Positive Development Media Pvt. Ltd. / Regd. No: 232 / 073-74

Newbaneshwor
Kathmandu, Nepal

4479401


Editor : Mr. Divesh J.B. Rana Chairperson : Mr. Pratibedan Baidya