Traffic to remain suspended for six hours a day along Narayangadh-Muglin road

Narayangadh Mugling HighwayChitwan / March 21: Vehicular movement along the Narayangadh-Muglin road section is to come to a halt for six hours daily to expedite the ongoing road upgrading task so that it can be completed before the arrival of the rainy season. The new provision will come into effect from March 28.

Presently, vehicles are prevented from plying on the 36- kilometre section from 10:30 am to 3 pm (four and half hours) in a day in view of the ongoing road widening works. The decision to increase the duration for the suspension of traffic movement by an additional one and half hours is aimed at making the works more effective, according to project’s Engineer Shiva Khanal.

The project in cooperation with the local administration plans to complete earthmoving works and construction of other important structures before the start of the rainy season.

Chitwan’s Chief District Officer Narayan Prasad Bhatta said the plans have been set to complete works relating to major road structures by the end of May to avert possible problems resulting from rains in the widening efforts. Around 7000 vehicles ply on the road every day. RSS

Related News

Comments are closed

TOP NEWSview all

Japan Hands Over the Sanitary Napkin-Making Machine in Parsa

Mayor Shah directs employees to reduce visits, seminars

Veteran singer, musician Bhakta Raj Acharya passes away

Trade deficit of Rs 811 billion in first seven months

WHO congratulates Nepal for legislation to restrict trans-fatty acids in food




Positive Development Media Pvt. Ltd. / Regd. No: 232 / 073-74

Newbaneshwor
Kathmandu, Nepal

4479401


Editor : Mr. Divesh J.B. Rana

Chairperson : Mr. Kishore Thapa


Counter:
Web Counter